Engineering CAM
Validate remaining hours and skill mix against the resource-loaded work plan.
Review: Before Period 07 forecast
Evidence: Approved hours/rates workbook and assumptions log
Illustrative Example · Synthetic Data
Summit Demonstration Program is fictional. All figures illustrate report structure and analytical reasoning, not a client engagement, contract award or achieved result.
Download the Synthetic Review Pack
KEYSTONEREPORTING GROUPIllustrative Example · Synthetic DataCost is outpacing earned progress. Review the remaining labor mix and the assumptions supporting the $7.80M estimate to complete.
| Measure | Amount | Calculation |
|---|---|---|
| Budget at Completion | $12.00M | Illustrative baseline |
| Actual Cost | $5.33M | Cumulative recorded cost |
| Estimate to Complete | $7.80M | Bottom-up remaining work |
| Estimate at Completion | $13.13M | Actual cost + ETC |
| Variance at Completion | −$1.13M | Budget − EAC |
| Cost Variance | −$0.53M | Earned value − actual cost |
| Schedule Variance | −$0.20M | Earned value − planned value |
EAC is a bottom-up forecast, not BAC ÷ CPI. SPI measures earned-value progress against plan; it does not establish a completion date or critical-path delay. No agency, contract or client is represented.
Synthetic Review · 01
Earned progress trails plan while the bottom-up forecast rises. The trend tells the reviewer where to investigate, not why the movement occurred.
Dashed Teal: Planned ValueNavy: Earned ValueCopper: Actual Cost
| Period | Planned Value | Earned Value | Actual Cost | ETC | EAC |
|---|---|---|---|---|---|
| 01 | $0.60M | $0.58M | $0.60M | $11.40M | $12.00M |
| 02 | $1.35M | $1.30M | $1.38M | $10.72M | $12.10M |
| 03 | $2.20M | $2.10M | $2.28M | $10.02M | $12.30M |
| 04 | $3.10M | $2.95M | $3.25M | $9.30M | $12.55M |
| 05 | $4.00M | $3.85M | $4.30M | $8.50M | $12.80M |
| 06 | $5.00M | $4.80M | $5.33M | $7.80M | $13.13M |
The prior $12.80M EAC rises by $0.33M: $0.20M for remaining labor mix and $0.18M for integration rework, partially offset by a $0.05M material estimate reduction. Unrounded movements reconcile to $13.13M.
The $12.00M budget is unchanged. The $7.80M ETC is a bottom-up estimate, assumes no additional scope change, and is subject to account-owner review. It is not a statistical forecast or a promised outcome.
Synthetic Review · 02
| Account | Earned Value | Actual Cost | Cost Variance | ETC |
|---|---|---|---|---|
| Engineering | $2.60M | $2.95M | −$0.35M | $4.20M |
| Integration | $1.40M | $1.50M | −$0.10M | $2.30M |
| Program Support | $0.80M | $0.88M | −$0.08M | $1.30M |
| Program Total | $4.80M | $5.33M | −$0.53M | $7.80M |
The $0.35M unfavorable cost variance accounts for about 66% of the program’s cumulative cost variance. In this illustration, the working hypothesis is a more senior labor mix and additional rework. Validate hours, rates and earned-progress evidence before treating that hypothesis as the root cause. Neither CPI nor SPI alone establishes causation.
Validate remaining hours and skill mix against the resource-loaded work plan.
Review: Before Period 07 forecast
Evidence: Approved hours/rates workbook and assumptions log
Confirm rework scope and inspect schedule dependencies before proposing recovery.
Review: Next technical review
Evidence: Work-package estimate and schedule impact review
Reconcile the material estimate and record whether savings are supported.
Review: Period 07 close
Evidence: Source reconciliation and reviewed EAC bridge
All owners, deadlines and actions are illustrative. No client delivery or achieved result is represented. SPI is not a completion-date or critical-path measure.
Download the Synthetic Review PackAt period 06, earned value is $4.80 million against $5.00 million planned value and $5.33 million actual cost. CPI is 0.90 and SPI is 0.96. These are cumulative cost and earned-value schedule indicators; they do not identify a root cause on their own.
The bottom-up ETC is $7.80 million. Actual cost plus ETC produces a $13.13 million EAC, $1.13 million above the $12.00 million budget at completion.
EAC = AC + ETC; CPI = EV / AC; SPI = EV / PV; CV = EV − AC; SV = EV − PV; VAC = BAC − EAC. Values are rounded for display. The ETC is an illustrative planning assumption, not mechanically derived from CPI.